13-5-1. Application.
A major subdivision is a division of land into 15 or more lots. Subdivisions with 100 or more lots must include a master plan of the entire community. The master plan will be reviewed by the planning commission during the concept stage where the commission may approve or deny the plan. A major subdivision of more than 25 lots shall be phased for development. Infrastructure and public facilities shall be dedicated. Phased developments may be excused from statutory time limits imposed by this chapter if the planning commission agrees to receiving progress updates by the developer every six months. All commercial or industrial land divisions shall only be done as a major subdivision. (Ord. 2011-05, 2/1/11; Ord. 2005-21, 9/6/05)
|
 |