13-5-3. Phase development .
(1) The preliminary and final platting of subdivisions containing more
than 25 lots shall be done in phases, except as provided in Subsection
(3). Development shall be performed so that the phases will be contiguous
and the required improvements will be continuous.
(2) When off-site improvements are complete and approved by the county
engineer and the lots are 70 percent sold, the subdivider may submit
the next phase for final plat approval.
(3) A preliminary and final plat including more than 25 lots will be
accepted only upon the submission of evidence indicating that the
market absorption rate is such, and the financial ability of the subdivider
is such that the off-site improvements for all lots in the final plat
will be completed within two years.
(4) Where it is prudent to engineer road or utility lines that extend
into the next phase, such work may be done if shown in the prior phase.
(Ord.2005-21, 09/6/05)
|