13-7-11. Sanitary sewer mains, laterals, and
house connections – Future .
Where county and regional general plans indicate that construction or
extension of sanitary sewers may serve the subdivision area within
a reasonable time, the planning commission may require the installation
and capping of sanitary sewer mains and house connections by the subdivider
in addition to the installation of temporary individual on-lot sewage
disposal systems. Whenever individual on-lot sewage disposal systems
are proposed, the subdivider shall either install such facilities
or require by deed restrictions or otherwise as a condition of the
sale of each lot or parcel within such subdivision that those facilities
be installed prior to or during the construction of the principal
building. No building permit shall be issued until such installation
is assured. In all other cases, sewage disposal facilities shall be
provided for every lot or parcel by a complete community or public
sewer system. (Ord.2005-21, 09/6/05)
|
 |