14-1-8. Building permits required for off-site
improvements.
All off-site improvements within Tooele County, except
those off-site improvements installed pursuant to the subdivision process,
shall be required to be done with a building permit and fees collected
therefore shall be according to the fee schedule for building permits
then in effect. Such fees shall be payable prior to issuance of the permit.
For purposes of this section, off-site improvements shall include the
installation of sidewalk, curb and gutter, roads, water and sewer lines
and the like. A separate building permit for any given structure may be
obtained in connection with doing the off-site improvements, provided
that the valuation of the off-site improvement shall be included in the
computation of the permit fee. A failure to comply with this section shall
result in the same penalties as are applicable for building permits under
the Uniform Building Code. (Ord.
95-19, 9/12/95; Ord. 9-5, 9/1/92)
|
 |